Environmental Impact Assessment (EIA) is a process that identifies both the positive and negative environmental effects of proposed developments prior to planning permission being considered. It aims to prevent, reduce or offset any identified significant adverse environmental effects of development proposals.

The EIA process is a method of ensuring that planning decisions are made in the full knowledge of the environmental effects and with full engagement of statutory bodies, local interest groups and members of the public.

The requirement for an EIA will only affect a small number of projects in Jersey. Below is the list of developments which will require an EIA. Any changes or extensions to a development that was previously subject to an EIA will also require an updated EIA.

If you're still unsure or consider that you shouldn't be required to undertake an EIA, you can complete an EIA advice request form. If you are undertaking an EIA and want to know what you need to provide, you can also request this on the EIA advice request form.


An EIA will be required if the proposal involves the:

  • change of the use of uncultivated or semi-natural land to use for an intensive agricultural purpose and where the area of the land exceeds 0.5 hectares
  • development of a water-management project for agriculture, including irrigation or land drainage project and where the area of the project exceeds 0.5 hectares
  • construction or installation of an intensive livestock installation and where the area of the installation exceeds 0.5 hectares
  • development or construction of an installation to rear fish and where the area of the installation exceeds 0.5 hectares

An EIA will be required if the proposal involves the:

  • extraction of peat
  • carrying out of deep drilling, including, in particular
    • geothermal drilling,
    • drilling for the storage of nuclear waste material, or
    • drilling for water supplies, but excluding drilling to investigate the stability of the soil
  • extraction of minerals(other than metalliferous and energy-producing minerals) including, in particular, marble, sand, gravel, shale, salt, phosphates and potash
  • extraction of coal or lignite, whether by underground or open-cast mining
  • extraction of petroleum
  • extraction of natural gas
  • extraction of ores
  • extraction of bituminous shale
  • extraction of minerals (other than metalliferous and energy-producing minerals) by open-cast mining
  • extraction of minerals by fluvial or marine dredging, except maintenance dredging
  • development of a surface industrial installation for the extraction of coal, petroleum, natural gas or ores or bituminous shale
  • installation of a coke oven for the dry distillation of coal
  • construction of an installation for the manufacture of cement

An EIA will be required if the proposal involves the:

  • construction of a power station or an installation for the production of electricity, steam or hot water, not being a domestic scale solar panel or wind turbine
  • construction of an industrial installation to
    • carry gas, steam or hot water, or
    • transmit electrical energy by overhead cables
  • construction of an installation for the surface storage of natural gas, where the
    • area of any new building or structure exceeds 500 square metres, and
    • installation will be sited within 100 metres of a stream, pond or reservoir
  • storage of combustible gas underground, where the
    • area of any new building or structure or the storage area exceed 500 square metres, and
    • storage area will be sited within 100 metres of a stream, pond or reservoir
  • surface storage of fossil fuel, where the
    • area of any new building or structure, or the deposit exceed 500 square metres, and
    • deposit will be sited within 100 metres of a stream, pond or reservoir
  • provision of an installation for the industrial briquetting of coal or lignite
  • construction or change of use of an installation for the production or enrichment of nuclear fuel
  • construction or change of use of an installation for the reprocessing of irradiated nuclear fuels
  • construction or change of use of an installation for the collection or processing of radioactive waste

An EIA will be required if the proposal involves the construction or change of use of an installation for

  • an ironworks or steelworks, including a foundry, forge, drawing plant or rolling mill
  • the production (including smelting, refining, drawing and rolling) of non-ferrous metals, other than precious metals
  • the pressing, drawing or stamping of large castings
  • the surface treatment and coating of metals
  • boiler making or manufacturing reservoirs, tanks and other sheet-metal containers
  • the manufacturing or assembling of motor vehicles or manufacturing motor-vehicle engines
  • use as a shipyard
  • the construction or repair of aircraft
  • the manufacture of railway equipment
  • swaging by explosives
  • roasting or sintering metallic ores

An EIA will be required if the proposal involves the construction or change of use of an installation for the manufacture of glass

An EIA will be required if the proposal involves the construction or change of use of an installation for the

  • treatment of intermediate products and the production of chemicals
  • production of pesticides or pharmaceutical products, paints or varnishes, elastomers or peroxides
  • storage of petroleum or petrochemical or chemical products

An EIA will be required if the proposal involves the construction or change of use of an installation for

  • the manufacture of vegetable or animal oils or fats, where the new floor area of the installation exceeds 1000 square metres
  • the packing or canning of animal products, where the new floor area of the installation exceeds 1000 square metres
  • the manufacture of dairy products, where the new floor area of the installation exceeds 1000 square metres
  • brewing or malting, where the new floor area of the installation exceeds 1000 square metres
  • confectionery or syrup manufacture, where the new floor area of the installation exceeds 1000 square metres
  • the slaughter of animals, where the new floor area of the installation exceeds 1000 square metres
  • the manufacture of industrial starch, where the new floor area of the installation exceeds 1000 square metres
  • use as a fish-meal or fish-oil factory, where the new floor area of the installation exceeds 1000 square metres
  • use as a sugar factory, where the new floor area of the installation exceeds 1000 square metres

An EIA will be required if the proposal involves the construction or change of use of an installation

  • for use as a wool scouring, degreasing or bleaching factory, where the new floor area of the installation exceeds 1000 square metres
  • to manufacture fibre board, particle board or plywood, where the new floor area of the installation exceeds 1000 square metres
  • to manufacture pulp, paper or board, where the new floor area of the installation exceeds 1000 square metres
  • for use as a fibre-dyeing factory, where the new floor area of the installation exceeds 1000 square metres
  • for use as a cellulose-processing or production installation, where the new floor area of the installation exceeds 1000 square metres

An EIA will be required if the proposal involves the construction or change of use of an installation to manufacture or treat elastomer-based products.

An EIA will be required if the proposal involves the:

  • carrying out of an industrial estate development project, where the area of the development exceeds 0.5 hectares
  • carrying out of an urban development project, including the construction of shopping centres, car parks, sports stadiums, leisure centres and multiplex cinemas, where the floor area of the buildings included in the project exceeds 10,000 square metres
  • installation of a cable-car
  • construction of a road, where the area of the road, including any pavements, exceeds 0.5 hectares
  • construction of a harbour, including a fishing harbour
  • construction of an airport
  • canalisation or flood-relief works, where the area of the canal and any auxiliary work exceeds 0.5 hectares
  • construction of a dam or any other installation designed to hold water or store it on a long-term basis, where the area of the dam or installation exceeds 0.5 hectares
  • construction of a tramway, elevated or underground railway, suspended line or similar line
  • construction of an oil or gas pipeline installation
  • installation of a long-distance cable for the transmission of electricity
  • construction of a long-distance aqueduct
  • construction of a marina
  • construction of coastal works to combat erosion, (but not the maintenance and reconstruction of such works)
  • construction or placing of maritime works that are capable of altering the coast by virtue of their construction or placement

An EIA will be required if the proposal involves the:

  • construction of a holiday village or hotel complex and associated developments in a rural location, where the area of the development exceeds 0.5 hectares
  • construction of a permanent racing or test track for cars or motor cycles
  • laying out of a golf course and the construction of any associated development, where the area of the course and any associated development exceeds 0.5 hectares
  • construction of an installation for the disposal or treatment of waste (including waste from mines and quarries and vegetable waste)
  • construction of a waste water treatment plant, including a treatment plant that forms part of any other development, where the area of the plant exceeds 0.5 hectares
  • change of use of land to use as a site for the deposit of sludge(but not treated or pelleted sludge)
  • change of use of land to use as a site for the storage of scrap metal, where the land is within 100 metres of a stream, pond or reservoir
  • installation of a test bench for engines, turbines or reactors, where the area of new floor space of the development exceeds 1000 square metres
  • construction or change of use of an installation to manufacture artificial mineral fibres, where the area of new floor space of the development exceeds 1000 square metres
  • construction or change of use of an installation to manufacture, package, load or place in cartridges gunpowder or other explosives, where the area of new floor space of the development exceeds 1000 square metres
  • construction or change of use of an installation or the change of use of land for use as a knackers yard, where the area of new floor space of the development exceeds 1000 square metres
  • development on land covered or, in the normal course of tides, from time to time covered by sea water
  • reclamation of land from the sea